Croxton, NJ Terminal Paving Project

ATLANTA, GA

We would like to inform you of a pavement improvement project at our Croxton, NJ Intermodal Facility that is underway, effective immediately today, Monday, August 17, 2026.

 

To minimize operational impacts, the project will be completed in multiple phases. The initial phase schedule is outlined below.

 

Project Schedule

 

August 17 – August 21 – Repairing and replacing storm water catch basins between pad tracks and parking rows G & H. Drivers need to be aware of crews working trackside and related potential slowness of working trains.

 

August 24 – TBD – The main entrance and gates (outlined in red on the maps below) will be closed to truck traffic during Phase 1 of the paving. At this time, all truck traffic will be rerouted to our emergency gate at 75 County Rd (marked with red arrow on the maps below).

 

During construction, traffic patterns and access routes may be temporarily adjusted within the terminal. We ask that all drivers and visitors follow posted signage and the directions of on-site personnel to ensure everyone’s safety, and to help maintain efficient terminal operations.

 

No shipment departure or availability delays are expected during the project. We appreciate your patience and cooperation as we complete these improvements. Updates will be provided if the schedule changes due to weather or other unforeseen circumstances.